The formula
Price Index Multiple = 70% × (WPI now ÷ WPI at base) + 30% × (CPI(IW) now ÷ CPI(IW) at base), where the base is the reference index before the bid date. Under the hybrid annuity model the bid project cost is indexed this way until the commercial operation date, and the O&M payments are indexed too (CARE Ratings HAM methodology, October 2022).
Indexed amount = amount at bid prices × PIM. WPI is published by the Office of the Economic Adviser (DPIIT) and CPI(IW) by the Labour Bureau. If an index series is rebased, use the official linking factor so that both values are on the same base.
To see the full HAM payment profile, use the HAM annuity schedule (L), and read BOT, TOT and HAM.